Infrastructure
Canton ends topology freeze on its test network
Blockdaemon marked the testnet maintenance complete on November 25 at 14:00 UTC. The operator announced a separate December 11–12 window for mainnet.

Topology changes waited a day
Canton’s test network completed a topology freeze on November 25 at 14:00 UTC, a day after it began at the same time, according to node operator Blockdaemon. The operator described the window as a testnet-wide event coordinated by the Canton Foundation to prepare for a synchronizer upgrade. It announced the end of maintenance at the originally scheduled time. Its notice specifies the start and end of the window and describes which operations had to wait.
During the freeze, applications that were already configured could keep submitting ordinary transactions, according to the operator’s notice. Topology changes had to wait. Blockdaemon cited onboarding validators, deploying new contracts, and uploading DAR archives, which bundle Daml packages. A team could therefore rehearse a scenario using contracts already in place. A test that began with adding a validator or submitting a new package depended on those operations reopening.
The freeze lets operators transfer network state
Canton’s documentation distinguishes the logical synchronizer, to which participants remain connected, from the physical infrastructure that orders operations at any given time. A logical upgrade moves participants to infrastructure that runs a different protocol version. Super validators can deploy the successor’s components before the switch. When the freeze starts, their automation transfers the topology state to those new components.
The freeze gives operators a reference state against which to check the successor’s readiness. The documentation calls for health-check events on the new infrastructure before it takes over. This phase takes place while applications can still use the existing synchronizer. At the switch, according to the documentation, processing resumes on the successor. Daml transactions prepared before the switch but submitted afterward must be prepared and signed again.
A separate mainnet window in December
Blockdaemon’s maintenance completion notice gives teams testing an integration a reference point for resuming deferred work. The notice provides no availability records for individual applications. Teams can therefore distinguish the end of the shared window from the success of their own deployments. That distinction matters particularly for tests involving several steps, such as uploading a package, validating it, and then submitting a transaction.
For mainnet, the operator published a separate notice. The freeze is scheduled from December 11 at 14:00 UTC to December 12 at 14:00 UTC. Blockdaemon says the window may be extended depending on the progress of the upgrade. Ordinary transactions are expected to remain possible during the freeze, while topology operations will be suspended. The testnet window shows which tasks are affected. The mainnet timetable follows its own notice.